Edenville Energy to proceed with Rukwa coal to power project in Tanzania

Posted on : Wednesday , 19th July 2017

 n early 2017 a new Power Master Plan Update was released by the Government of Tanzania that included the Edenville Energy project.

 
This plan is now being progressively rolled out by the government of Tanzania to provide further power generation and transmission for the country over the long term up to 2040.
 
The project has already had a feasibility study carried out in 2015 for a 120 MW power generation facility and the Ministry of Energy has indicated a larger facility of up to 300 MW can be constructed at Rukwa, assuming technical, financial and commercial parameters can be satisfied.
The 120 MW project returned an NPV10 of US$252 million and an IRR of 23% from recent independent financial modelling carried out in late 2016.
 
In January 2017 Edenville Energy signed a Memorandum of Understanding with Sinohydro Corporation of China to complete a bankable feasibility study on the project.
 
Edenville Energy and Sinohydro will be looking at all options to optimise the power plant size and to source suitable funding from recognised financial institutions for construction of the Project.
 
In parallel with this, talks will take place with The Tanzanian Electric Supply Company to finalise the power purchase agreement and associated transmission infrastructure that will be needed to take the electricity.
 
Edenville Energy holds 100% of Edenville Power Tanzania, the company registered in Tanzania to develop and operate the project.
 
Edenville Energy through its Tanzanian subsidiary Edenville International Tanzania also holds the Mkomolo mining licence ML562/2016 and a 90% interest in the coal deposits at Rukwa.
 
New access road permit granted for coal mine
 
Edenville Energy has also received permission to upgrade and where necessary construct, a new access road that will connect the site with the main north south sealed highway to the west of the project.
 
The road will be approximately 16 km long and allow coal trucks to reach the site more efficiently than the current transport infrastructure. Ultimately this road will also be used as part of the power plant access infrastructure.
 
Work is commencing on the road immediately and Edenville Energy expects a usable road to be completed by the end of June 2017.
 
“The request from the Ministry of Energy and Minerals is a very significant step forward in the timeline for the development of the project,” says Edenville Energy CEO, Rufus Short.
 
“The project can now move forward, working alongside the Tanzanian authorities, to ultimately provide significant electricity expansion to the country,” he continues.
 
The start-up of the coal mine to provide commercial coal sales will undoubtedly assist the power plant development as this will give a significantly greater understanding of the coal that will be used for power generation.
 
“The next few years will be an extraordinarily busy and transformative time for the company as both the mine and the power plant are developed, and I look forward to providing regular updates as and when appropriate,” concludes Short.

Source : https://www.miningreview.com
Featured Companies
  • dubaiexporters.com

Complete List  

Advertisers in previous issue:

  • Speco Ltd. is the leading manufacturer & supplier of Asphalt Mixing Plant, Concrete Batching Plant, Crushing Plant & Optimized Integrated Flue Gas Treatment System.
  • IAC understand your system requirements, and can offer valuable input, be it design, consulting, training, or technical support.
  • Engineering Expo, is India’s largest multi-location trade show on manufacturing
  • From a modest beginning in 1955, the IGP Group today provides over 50 products and services to the core sector.
  • Automatic brick manufacturing machines
  •  ABL Machine Tools, One of the group companies of ABL India is India
  • South African incinerator and cremator designer and manufacturer making significant inroads into overseas markets.
  • Luminous Power Technologies Limited is a leading company with a differentiated portfolio of solutions for packaged power, diversified generation, electrical control & safety and energy optimization.
  • Bakery Equipment, Flour Mill, Bread Improver, Dried Fruit Processing machine
  • EMI has a qualified and dedicated team of managers with vast experience in their respective areas of work.
  •  JS Electromec Ltd,(JSE Ltd) are registered Electrical contractors and Suppliers of Lighting and Power solutions for residential, commercial and industrial applications in Tanzania.
  • Shenzhen City, Riland Industrial Co., Ltd. is China
  • Producing numerous types of welding consumables and welding machines for both the domestic and international market
  • Anya energy limited is accredited with ISO 9001 certification for Quality Management System and our products are recognized and certified by Bureau of Indian Standards
  • We offers high quality, Competitive price and satisfied service always
  • All type conveyor belts for internal & external location tapis roulant de tout genre pous deplacement a l
  • Multi feedstock batch processing biodiesel equipment
  • YorPower Kenya was established in 2002. From our headquarters in Nairobi we sell Diesel Generators manufactured by our parent company,
  • Manufacturer of heavy duty machinery
  • BITZER ranks among the leading manufacturers of refrigerant compressors.
  • KJV is a professionally managed group in distribution & transmission sector involved in executing contracts
  • Chemicals,Environmental & Sewage,Treatment Laborotory;Equipments Analytical Equipments & Instraments;etc.
  • Save your power bill by instaling servo voltage stabilizer.
  • Catering for the most varied industrial storage requirements.
Afrotrade International Marketing, Tel: +971-50-6285684
© 1998-2025 Afrotrade