Ethiopia: Geothermal Plant to Be Operational in April - Ministry
Ethiopia is striving for the operation of the Aluto-Langano geothermal power plant with installed capacity of 70mw power in this fiscal year, the Ministry of Water, Irrigation and Energy said.
Energy Study and Development Follow-up Director, Gosaye Mengistie said over 78 percent of construction of the geothermal plant has so far been finalized.
It is expected that the plant will commence operation in.... Read more »
Posted on : Monday , 15th September 2014